Halifax Bank of Scotland, Leeds

HBOS Plc initially requested TB+A to investigate the impact of the European Regulation EC 2037/2000, which states phase out dates of various refrigerant types, and its impact on the HBOS Plc corporate sites.

From this, several sites were identified as chiller replacement projects, including surveying of installation for M&E equipment and overall usage, designing replacement solutions and acting as the Employer’s Agent for project management

  • Westbank, Leeds - upgrade air conditioning system due to expansion, replacement of main items of plant including chillers and air handling units. TB+A were Lead Consultants.
  • Lovell Park, Leeds - surveys and reports on M&E services. Lead Consultant / Employer’s Agent for primary plant replacement.

< Back to Projects...

AREA
various

CLIENT
Halifax Bank of Scotland

SERVICES PROVIDED
M&E Engineers

OFFICE
Leeds

COMPLETION
2012